Board Meeting January 22, 2026 at City Hall 2nd Floor Meeting Room
2025
Road Repairs to East Ridge Road
CLOSED
3 contractors were invited to bid. In total 2 bids were responsive. A forth bid was solicited by a community member and presented to the Board. That bid was disqualified as it did not meet the terms outlined in the RFP. Heart 7 was the lowest bid.
This contract was awarded to Heart 7 Enterprises LLC on 11/26/25 by a Special Meeting of the Board. This work is now complete.
2024
Road Repairs Portions of Bearpaw Creek Road - Closes August 30, 2024
CLOSED
8 contractors were invited to bid; 6 from Columbus, 1 from Billings & 1 from Roberts. In total 3 bids were received.
This contract was awarded to Heart 7 Enterprises LLC on 09/09/24. Work is anticipated to commence on 09/23/24.
Snowplowing Services 2024-2025 Season - Closes September 13, 2024
CLOSED
13 contractors were invited to bid. In total 1 bid was received.
This contract was awarded to Heart 7 Enterprises LLC on 09/25/24. The contract is effective 10/01/24.